Simulation construction procedure and Testing analysis of Double-arch Tunnel
XIE Ai-hua1
(1 ShiJiaZHuang Railway Institute, shijiazhuang 050043, China)
Abstract: By adopting the calculating analysis method of FEM simulation, this paper makes a simulation analysis on the excavating procedure of the No.1 Yehuling Tunnel on the expressway from Zhangjiakou to Shijiazhuang, so that the stress situation of the excavating procedure can be known, and combined with the site monitoring and data analysis for permanent lining , to estimate the structure stability and give some reference to the tunnel construction.
Key words: Double-arch Tunnel; FEM Simulation; Permanent Lining; Monitoring and Measuring; Lining Structure Stress
1工程概况
张石高速公路野狐岭1#隧道起讫里程为K19+840~K20+400,全长560 m,位于野狐岭段玄武岩台地区,恰处分水岭(山脊)和垭口重合地段;该隧道**大埋深位于隧道中部偏后为16.8 m,进出口段埋深1~2 m,其余埋深5~8 m,属于浅埋隧道。隧道围岩主要为Ⅴ级围岩,进口地段围岩以强风化碎块状玄武岩为主,次为亚粘土,地表风化强度更强,岩质疏松;出口地段主要为弱-强风化碎块状结构,次为碎石土;中部地段岩石风化程度较进口段弱,也以强风化碎块状玄武岩为主。由于岩体风化差异,致使疏松岩石与坚硬岩块相间出现,开挖过程很难控制开挖断面形状,施工困难。
隧道横断面采用双跨连拱断面设计,净宽10.25 m,建筑限界高度5.0 m,净高7.05 m。衬砌断面采用单心圆方案,半径为5.43 m,以利于结构受力以及便于施工。隧道平面布置主要服从路线总体走向,采取平曲线,纵坡坡度2.673%。具体尺寸如图1所示。
图1 隧道断面图
Fig.1 The Cross Section of the Tunnel
施工中遵循“先支护、后开挖、短进尺、弱爆破、快封闭、勤量测”的施工原则进行开挖施工。对于隧道洞口采用明挖法施工,隧道洞身段采用三导洞先墙后拱法施工,中导洞先行,左导洞滞后中导洞,右导洞滞后左导洞,导洞均采用正台阶法施工,台阶长度5-7 m,开挖进尺按两榀钢架间距进行。主洞开挖先进行左洞,右洞滞后左洞7-10 m。主洞开挖亦采用台阶法,上台阶分部开挖预留核心土。
2 有限元计算与分析
采用ansys